PCB allows RSP to resume operation

Last Updated: Sunday, January 22, 2012 - 16:03

Bhubaneswar: Four days after shutdown of
two units at Rourkela Steel Plant (RSP), Odisha`s State
Pollution Control Board (SPCB) has granted permission to
operate them following anti-pollution measures and submission
of a time-bound action plan.

RSP sources said that based on a comprehensive
time-bound action plan presented by it before the board last
week and the action already taken for pollution control at two
units, they have been granted permission to operate them.

In compliance with the directive of SPCB, they had
shut down these two units on January 16.
In a statement the company affirmed its commitment
towards fulfilling the action plans on emission control in a
time-bound manner.

While closing down the two units, RSP undertook
various process improvement steps to modify its pollution
control measures.

A delegation of RSP led by its CEO G S Prasad had
assured the SPCB that concrete steps were being taken to
rectify certain lacunae by putting in place the action plan.