Series of tests are on for Kudankulam atomic power plant

Even as the first reactor of Kundankulam plant started generating electricity and was connected to the grid on Tuesday, a series of tests are in progress lined up before the plant reaches its full capacity, a nuclear energy expert said on Thursday.

New Delhi: Even as the first reactor of Kundankulam plant started generating electricity and was connected to the grid on Tuesday, a series of tests are in progress lined up before the plant reaches its full capacity, a nuclear energy expert said on Thursday.

This includes profile tests for the basic systems and equipment of the unit, with the unit operating at different levels of electric capacity.

The 1000MW unit is the first reactor at the Kudankulam Nuclear Power Plant Project (KKNPP), which is being built by the NPCIL with Rosatom, Russia`s State Energy Corporation. The second unit (reactor) should reach the criticality stage in six months, sources said.

"Compliance of the actual and design values of the basic parameters of the reactor and the power unit as a whole will be confirmed. Time period required for carrying out all this work is likely to take six months," said a Russian nuclear expert Alexandr Uvarov, who is also the editor-in-chief of the atominfo.Ru, a website catering to nuclear news and nuclear scientists.

The tests are conducted at different stages when the plant starts generating 50 percent of the capacity, followed by 75 percent and then subsequently 100 percent.

The tests also include disabling of the basic systems of the unit and testing its stability in this situation.

"At the same time, an entire series of tests take place with the power unit disconnected from the power grid,". These tests are mandatory as prescribed by the Atomic Energy Regulatory Board (AERB) of India.

Uvarov added "the next stage follows which is the integrated testing of the power unit. At this stage, the unit is supposed to have worked without interruption for 72 hours, at the capacity of 100 percent."

During this time, one has to ensure that the equipment, the automatic control systems and the safety and control systems operate in a reliable, correct and cost-effective way.

"For a test to be considered as successfully passed, it is essential that during the test, safe operation limits and conditions are observed, water chemistry of the primary and the secondary circuits should comply with the regulatory requirements. Also, the parameters of the equipment and the systems are not beyond the deviation limits established by the project," he said.

After performing the tests, the time comes for the preliminary acceptance of the unit, which is followed by 1-year period of operation.

Uvarov said modern nuclear plants have a life-capacity of 60 years but its life can be extended up to 80-100 years.