Delhi's Ashram flyover extension nears completion, to be finished by November 2022
Three lanes of Ashram flyover will be for traffic going from south Delhi to Sarai Kale Khan, while the remaining three will be for vehicles going from ITO and Sarai Kale Khan to south Delhi.
- The total length of Ashram flyover, including the ramp, is 1,425 metres
- The total cost of the six-lane flyover is Rs 128.25 crore
- The flyover extension work started in June 2020
Trending Photos
The Ashram Flyover Extension Project will be finished by November, alleviating the commute of thousands of people between Noida and Delhi. The six-lane flyover will relieve congestion at the busy crossroads of Ashram Chowk. The initial deadline for constructing the flyover was September of this year, according to PWD officials. Manish Sisodia, the deputy chief minister, visited the building site to assess its progress and gave instructions for installing more equipment to speed up the process.
"It was a herculean task to build a flyover in the middle of such a busy Ring Road, but the PWD engineers undertook this daunting challenge and delivered. Ashram flyover extension work in full swing, to be completed for citizens use by November," Sisodia said in the statement.
Benefits of Ashram flyover extension
He said that after the completion of this flyover, lakhs of people commuting from Noida and other parts of Delhi to the southern part of the city will be freed from cumbersome traffic jams. The flyover will allow passengers to bypass three traffic signals between Ashram Chowk and DND Flyway, making vehicular movement smoother.
Also read: Noida Twin Tower demolition: Check roads to avoid, traffic diversions today
Details of Ashram flyover extension
The total cost of the six-lane flyover is Rs 128.25 crore. Three lane ramp will be for traffic going from south Delhi to Sarai Kale Khan, while the remaining three will be for vehicles going from ITO and Sarai Kale Khan to south Delhi.
The total length of the flyover, including the ramp, is 1,425 metres. LED lights will be installed to light up the flyover. Exquisite artwork will be done on the pillars, the statement said. Engineers told the minister that all the pillars of the flyover have been erected, and now, the work is going on to put girders on them using large cranes. These cranes require a lot of space to function, and this is possible only when the road is closed.
In such a situation, due to heavy traffic throughout the day, the traffic police has permitted construction work only from midnight to 5 AM. If there is an increase in the traffic during this time, the construction work is put on halt by the traffic police, the statement said.
PWD officials said that a total of 146 girders are to be installed on the existing pillars here, but due to the existing challenges, hardly 2-3 girders are installed in a day. Till now, a total of 56 girders have been placed, with 90 girders pending installation, the statement said.
"Deputy CM instructed the PWD officials that additional cranes must be installed to expedite the construction work, and the work of laying the girders should be done at double speed. The flyover extension should be completed at the earliest to relieve citizens from traffic jams,? according to the statement.
The flyover extension work started in June 2020. However, the work was stalled for a long time due to the closure of construction activities during the COVID-19 lockdown and later due to an increase in pollution levels.
It also took almost a year to obtain permission from the traffic police to start the construction, due to which the pace of work was reduced further, the statement said. Currently, vehicles coming and going from Noida and Ghaziabad to south Delhi have to grapple with jams while travelling from the DND loop to the Ashram intersection.
Currently, vehicles have to take a long route to cross the road from Kilokari, but soon, 150 meters away from Kilokari to Ring Road, drivers will be able to cross the road by taking a U-turn to reach Maharani Bagh or south Delhi. Similarly, vehicles going from Maharani Bagh to Sarai Kale Khan, Noida, ITO and Ghaziabad will not have to take long detours. A subway for pedestrians is also being constructed here, the statement said.
Stay informed on all the latest news, real-time breaking news updates, and follow all the important headlines in india news and world News on Zee News.
Live Tv