Rio Olympic Park nears completion
The construction work at Rio de Janeiro's 2016 Olympic Park complex has reached 92 percent completion, officials said.
Trending Photos
Rio de Janeiro: The construction work at Rio de Janeiro's 2016 Olympic Park complex has reached 92 percent completion, officials said.
Eleven of the 16 venues are more than 90 percent complete.
Arena da Juventude is the least advanced venue at Deodoro Park - the Games' second-largest sports cluster. The arena, which will host basketball and fencing, is 68 percent complete.
Construction of the athletes village and the main press centre is also nearing completion.