DMRC completes Phase IV tunneling work on Janakpuri West - RK Ashram Marg metro corridor

Delhi Metro Rail Corporation today achieved a milestone in Phase IV metro construction with the completion of tunneling work between Krishna Park Extension and Keshopur, reports IANS.

DMRC completes Phase IV tunneling work on Janakpuri West - RK Ashram Marg metro corridor Image Source: Twitter

Delhi Metro Rail Corporation (DMRC) achieved another milestone as it completed tunneling work between Krishna Park Extension and Keshopur on the Janakpuri West - RK Ashram Marg corridor. A Tunnel Boring Machine (TBM) broke through this morning at Krishna Park Extension after boring a 1.4-kilometer-long tunnel in the presence of the Secretary, Ministry of Housing and Urban Affairs and Chairman, DMRC Manoj Joshi, Managing Director, DMRC, Vikas Kumar and other senior officials. Officials stated that this tunnel breakthrough was achieved using a mammoth 73-meter-long TBM. The completion of this stretch is a significant achievement for DMRC since this work faced repeated constraints due to the pandemic.

Officials said that this tunnel breakthrough was achieved using a mammoth 73-meter-long TBM. Two parallel circular tunnels for up and down movement have now been constructed on this stretch, which is part of a 2.2-kilometer-long underground section from Janakpuri West to Keshopur. The work on the other parallel tunnel in this section was completed in December last year.

Also read: No more train delays! Indian Railways to soon introduce anti-fog devices for better visibility to loco pilots

The workforce was retained following all the guidelines, and the work schedule was planned accordingly. On this underground stretch, apart from the twin tunnels, the ramp and the entry/exit have been completed while about 70 percent of the Krishna Park Extension station has also been completed. Civil work of this particular underground section will be completed by early next year though the entire Janakpuri West - RK Ashram Marg corridor will be ready by September 2025.

This new tunnel stretch is a continuation of the earlier Magenta line tunnel that was already constructed for the presently operational Botanical Garden - Janakpuri West corridor. The tunnel has been constructed approximately at a depth of 14 to 16 meters. About 2,000 rings have been installed in the tunnel. It has an inner diameter of 5.8 meters. The alignment of the tunnel runs along the Outer ring road and below multi-storied built-up structures.

The tunnelling work involved innumerable challenges like shifting sewer lines at a depth of 8 meters using the micro tunnelling method. In addition, due to heavy traffic on the Outer Ring Road, a subway was constructed using the box-pushing method without disturbing the traffic flow.

Officials said that all necessary safety precautions were taken while constructing the tunnel below the built-up structures by monitoring the ground movements with highly sensitive instruments fixed on the nearby structures. With these measures, it was ensured that there was no settlement anywhere.

As part of the Phase IV work approved so far, 28.76 kilometers of underground lines will be constructed. The Janakpuri West-RK Ashram Marg corridor will have underground sections of 9.41 kilometers in total.

A TBM is a machine used to excavate tunnels with a circular cross-section through a variety of soil and rock strata. They can be designed to bore through anything from hard rock to sand. They have revolutionised the way tunnelling work is done worldwide as tunnels can now be bored without disturbing the buildings and other structures on the surface.