Hydro power project in Uttrakhand under environ min scrutiny

The Government has warned Alakananda Hydro Power Company Limited (AHPCL) of closure of its project in Uttarakhand for its failure to comply with environmental norms at the site.

New Delhi: The Government has warned
Alakananda Hydro Power Company Limited (AHPCL) of closure of
its project in Uttarakhand for its failure to comply with
environmental norms at the site.

"After examination of the monitoring report of the
Srinagar Hydro Electric Project, we found that the work for
the catchment area treatment is yet to be started by the
forest division.

"Similarly, afforestation and green belt work at the
site is yet to be commenced," an Environment Ministry official
said.

The ministry has also taken serious note of the fact
that a firm assigned to formulate plans for the stability of
slopes on the reservoir periphery through engineering and
biological measures had not submitted the report to it.

The official pointed out that while the company is
wanting on various environmental compliances, the site
inspection report has shown that construction work of the
project is going on a fast pace and it is likely to be
commissioned within next two years.

AHPCL is implementing the 320 MW project over Alaknanda
river in Srinagar under an agreement signed with governments
of Uttar Pradesh and Uttarakhand in February 2006.

Taking serious view in the matter, the ministry warned
the project promoter that if the work on environmental
compliances does not progress pari passu (in consonance) with
construction work, the same would be stopped.

It has asked the AHPCL to file a detailed time schedule
of construction vis-a-vis environmental compliances within two
weeks in the matter or face action.

PTI